Six people paint the fence and 15 hours how long would it take five workers to do the same job

Respuesta :

somaiasult2006
somaiasult2006 somaiasult2006
  • 02-01-2019
it will take 12.5 hrs for five workers to do the same job.


steps:

15 × 5 = 75

75 ÷ 6 = 12.5
Answer Link

Otras preguntas

Solve (x + 1)2 – 4(x + 1) + 2 = 0 using substitution. u = x 4(x +1) x +1 (x + 1)2 Select the solution(s) of the original equation.
2. What do fung grow from? A seeds B. flowers C spores & most D. fruit​
Points A, B, and C are collinear with coordinates A(-2,5), B(1,3), and C (x,-13). What is x?
Miscommunication example of listening
Find the difference quotient f(x+h)-f(x)/h, where h≠0, for the function below. f(x) = -4x² + 3x-5 Simplify your answer as much as possible.
What number gives a result of − 5 when 9 is subtracted from the quotient of the number and 4 ?
Whic type of “cell” is the most commonly used to convert solar energy into electricity
I just need to know the answer pls
Question 6 (6.03): Simplify. m9n7m6n
Tarleton State University-Central Texas was established when? a. 1999 b. 2005 c. 2010 d. 2015